Applies to:

ALL CUSTOMERS

Repositioning/Rewiring Air Valves for 220240V Model 690/390 fryers

Kit number

144050

Estimated Time

1 to 1.5 Hours

To avoid electrical shock or property damage, move the power switch to OFF and disconnect power.

  1. Disconnect power from fryer.

  2. Use a crosstip head screwdriver or cordless drill to remove the left side panel.

  3. Remove red cap from solenoid and slide nameplate sideways to release the valve coil (green). A flat blade screwdriver may help.

  4. Remove the spring around the barrel.

  5. Unthread the barrel section of the valve from the nipple on the pump and set aside for reuse.

  6. Use a crosstip head screwdriver, or cordless drill to remove the front control panel.

  7. Disconnect the air solenoid leads, remove the conduit, and discard. Reuse the 90° conduit connectors on the valve and frame bracket.

  8. Apply thread sealant to the nipple and attach ¼ NPT elbow. Apply thread sealant to both ends of 5” nipple and attach it to the elbow.

  9. Thread the existing valve onto the nipple using the port labeled “2”. Mount 90° connector to new valve, along with new conduit .

  10. Conduit may have to be formed by hand to mate with conduit on frame bracket.

  11. Ensure the nipple is angled, to keep the valve positioned above the pump outlet.

  12. Solenoid wiring: Locate wire terminals and wiring harness.

    • For 220-240V fryers: Using wire nuts, connect wire #90 to one solenoid wire and connect the other solenoid wire to wire #20 on fryer.

    • For 230V CE units: Remove or cut and cap wire #45 with crimp nut. Use crimp nuts to connect wire #90 to one solenoid wire and reconnect the othersolenoid wire to #44.

  13. Relay wiring:

    • For 220-240V fryers: cut wires 21 and 77 as close to the relay terminal as possible. Strip the ends, and connect all 4 wires together, wires 91, 92, 27 &77, using a wire nut. Then connect wires 91 and 92 to pump relay as shown in diagram below

    • For 230V CE fryers: cut wire 25 as close to the relay terminal as possible. Strip the end, and connect it to wire 91 using a blue terminal (EC02-003). Then connect wire 91 to pump relay as shown in diagram below. Wire 92 is not needed.

  14. Replace control panel and side panel and restore power to the fryer.

Related Content

Replacing the High Temperature Limit Control

Replacing the Temperature Probe

Replacing the Transformer

Replacing the Gas Control Valve

Replacing the Airflow Switch

Replacing the Air Valve

Replacing the Flame Sensor Assembly

Replacing the Ignitor Assembly

Replacing the Ignition Modules

Replacing the Blower Assembly

8 Head Baso Retrofit Kit

PFG-69X & OFG-39X Gas Valve Replacement Kit

Repositioning / Rewiring Air Valves for 120V Model 690/390 fryers

FM07-558 Gas Valve Replacement Kit

Ignition Module Retrofit Kits

Manifold Retrofit Kit Instructions

PFG 690/691 Ignition Module Kit

Mounting the OFG 390 and PFG 690 Vacuum Switch

PFG 690 and 691 Temperature Probe CE Instructions

Replace Gas Valve Assembly with Gas Valve and Solenoid Assembly

Replacing Gas Valve Assembly With Gas Valve and Solenoid Assembly

Air Switch Monitoring Retrofit Kit Instructions

CE Gas Valve Adjustment Instructions

I-Beam Cable Hole Plug Installation

FM08-502 8 Head Replacing KFC Control

FM08-481 8 Head Replacing the Control

Label Application and Location for the 8 Head Fryer

PFG-690/691 & OFG-390/391 Pump Motor Relay Kit

Pan Spacer Bracket

PFG 690 to 692 Retrofit Kit

Conversion From C8000 Control to KFC SMS Control

Rear Cover Removal Instructions

Replace Nylatron Slides on PFG 690 and 691

Installing Optional Crumb Basket

PFG 690 and 691 Installing Filter Rinse Hose

Installing the Pump Seal Kit

Unpacking Instructions

PFG 690 Stabilizer Retrofit Instructions

Conversion From Standard 690 Control to S/M Control

PFG 691 C8000 Retrofit Instructions

PFG 690 and 691 Lid Cable Replacement

Operating Instructions for PFG-691/OFG-391 Direct-Connect Oil System

Direct-Connect Retrofit Instructions (For use on fryers after SN: 391-LH016JC & 691-LH029JC)

Reference

PFG 690 and 692 Inspection and Planned Maintenance

Error Codes

PFG 690 Wiring Diagrams

Specifications

PFG 690 and 692 KFC Annual Inspection Certification